Monday 12 March 2012

PLANNING: Changes and Updates, New Shooting Schedule

Recently, a large problem was encountered within our filming project. Where we thought we had found reliable actors, unfortunate circumstances led to each of them deciding they were unable to continue with filming in time for the scheduled shoots.
The last-minute nature of their cancellations meant that we were thrown in at the deep end, and had to reschedule a few shoot-dates, change the plot of our film a lot and find new actors, all at the last minute.

Thankfully, we worked hard to make these changes and achieved them by the date necessary for shooting (10th March).
Due to this, the new shooting schedule is below, with each of the changes we had to make to accomplish our shooting. The dates and actors are edited and there is a new post introducing our actors.

To keep our teacher updated on the mini-crisis we had, we used our group's Twitter account to communicate with each other, our actors, and our teacher. This meant that we could get messages out to people quickly and easily.

Shooting Schedule

Scene
Actors Needed
Where?
When?
Costume/Props
Running scene (1st) inc. credit shots
Ella & Katie
Jimmy’s End
25th Feb
Normal teenage clothing
Desk/Writing scene
Ella/Katie
Jimmy’s End
26th Feb
Normal teenage clothing, paper, pen
Two guys indoor scene
Ben Richards, Robert Kostur
Jimmy’s End
10rd March
Normal teenage clothing, makeup for zombie
Fight scene zombie and guys, inc. Credit shots and final shot.
Ben Richards, Robert Kostur
Jimmy’s End
10rd March
Normal teenage clothing, makeup for zombie
Voiceover
Ella/Katie
Quiet room or Radio Box.
4th March (subject to change).
N/A


No comments:

Post a Comment